Atwood Subdivision

  • Client Name: Sideline Developments
  • Project Name: Atwood Subdivision
  • Location: Prince George
  • Sector: Civil
  • Timeline Start: 31 August 2023
  • Timeline End: 30 September 2023

Datoff undertook the construction of roadways for a 24-lot subdivision, which included a range of tasks to ensure proper infrastructure. This encompassed sloping and ditching to manage water flow, as well as working on culvert areas to facilitate drainage. Additionally, they improved the stability of certain areas by adding more crush material.

Upon completion, the team performed final compaction of the surfaces, tidied up the site and installed necessary signs for safe navigation.